Gantt view

Show your tasks as bars on a timeline based on their Timeline column. Ideal for planning projects with a start and an end.

Jun 26, 2026

Watch this step in the video · Gantt view

What it is and when to use it

The Gantt (timeline) view shows your tasks as horizontal bars along a timeline: each bar spans the task's date range. It's the best view for planning projects with a start and an end, seeing overlaps between tasks, and grasping the total span of the work. Like the Calendar, it reads the same tasks from the Table view with no reload.

Requirements

  • For bars with real duration, the board needs a Timeline column (a start–end range).
  • Tasks with only a Date column show as a single-day point instead of a bar.
  • A task with no date at all isn't drawn (it stays in the Table).

Which dates draw each bar

  1. If there's a Timeline column, the bar runs from its start to its end.
  2. Otherwise, a Date column is used (the one flagged Use as deadline, or the first one) as a single-day point.

Steps to use the Gantt view

  1. Open the board in Projects.
  2. If you don't have a range column yet, click + Add column and pick Timeline. Give your tasks a start and an end.
  3. In the view switcher at the top, click Gantt.
  4. You'll see one row per task, grouped by their group (with the group color). The time scale adjusts itself: it shows weeks on short projects and months on long ones.
  5. A line marks today when the current date falls within the visible range.
  6. Click a bar to open the task's detail.

Verify it works

Add a Timeline column, give a task a start and an end, and open the Gantt view: the bar should cover that range. A task with only a Date should appear as a point.

If it doesn't work

  • "Add a timeline or date column to use the Gantt chart": the board has no dates. Add a Timeline or Date column.
  • "No task has dates to show on the timeline": there are date columns, but no task has them filled in. Fill in start and end.
  • A task shows as a point instead of a bar: it only has a Date column, not a Timeline. Add a start–end range.

Tips

  • The Gantt is read-only in this version (no dragging the bars): adjust dates by opening the task or editing the Timeline cell in the Table.
  • Use the board's groups to separate project phases; the Gantt draws them in their color.